The Ordinance requires that the building owner shall within five (5) years after the “Date of Service” comply with the seismic retrofit regulations. A certified letter was sent to the owner of every URM building known to the City of San Diego, to the mailing address, known and on file with the San Diego County Recorder’s Office, notifying them of the “Date of Service” of January 1, 2001. More.

I cant really gove you an answer,but what I can give you is a way to a solution, that is you have to find the anglde that you relate to or peaks your interest. A good paper is one that people get drawn into because it reaches them ln some way.As for me WW11 to me, I think of the holocaust and the effect it had on the survivors, their families and those who stood by and did nothing until it was too late.