Some agencies are issuing BPAs against schedules for multi-million dollar amounts. Is there a dollar amount too large for MAS/BPA procedures?

No. The maximum order limitation requirement has been removed from MAS procedures. FAR 8.404 (b) (3) states that agencies may find it advantageous to request a price reduction where the ordering agency finds that a schedule product is available elsewhere at a lower price, or where the quantity of an individual order clearly indicates the potential for obtaining a reduced price.

Note that on Federal Supply Schedule contracts, the GSA Contracting Officer has already determined the prices to be fair and reasonable on the total value of the contract. More.

I cant really gove you an answer,but what I can give you is a way to a solution, that is you have to find the anglde that you relate to or peaks your interest. A good paper is one that people get drawn into because it reaches them ln some way.As for me WW11 to me, I think of the holocaust and the effect it had on the survivors, their families and those who stood by and did nothing until it was too late.

Related Questions